Earthwork Estimation in Construction: Step-by-Step Calculation with Example & Cost Analysis

Earthwork forms the foundation of any structure and must be accurately estimated.

Complete Example: Building Earthwork

Building 20m × 15m, Plinth 0.75m above GL, Foundation 1.5m deep

Step 1: Excavation Volume

Pit size = (20+2×1) × (15+2×1) × 1.5 = 22 × 17 × 1.5 = 561 m³

Step 2: Backfill Required

Foundation = 2(20+15) × 1 × 1.5 = 105 m³

Plinth fill = 20 × 15 × 0.75 = 225 m³

Total = 330 m³

Step 3: Surplus/Deficit

Surplus = 561 – 330 = 231 m³ to cart away

Cost Calculation

ItemQtyRateCost
Excavation561 m³₹200₹1,12,200
Backfill (compacted)330 m³₹150₹49,500
Cart away (with 25% bulking)288 m³₹100₹28,800
TOTAL EARTHWORK₹1,90,500

Bulking & Shrinkage Factors

Soil TypeBulking %Shrinkage %
Sandy soil10-15%5-10%
Clay soil20-30%10-15%
Rock30-40%15-20%