Labour Calculation in Construction: Step-by-Step Method, Formula, Rates & Examples

Labour typically accounts for 15-25% of total project cost.

Labour Categories & Rates

TypeDaily Rate (₹)Typical Skill
Unskilled300-500Carrying, digging, mixing
Semi-skilled500-800Plastering, tiling
Skilled800-1500Masonry, carpentry, steel work
Supervisor1500-3000Site supervision, QC

Labour Calculation Formula

Step 1: Labour Norm (work per labour day)

Labour Days = Total Quantity / Labour Norm

Labour Cost = Labour Days × Daily Rate

Example: Brick Masonry

Quantity: 1000 m²

Labour Norm: 5 m²/day per mason

Labour days = 1000 ÷ 5 = 200 days

Daily rate = ₹1000

Total labour cost = 200 × 1000 = ₹2,00,000

Common Labour Norms

WorkUnitNormWorkers
Brick masonry52 skilled + 2 helper
Concrete0.53 skilled + 5 helper
Plastering81 skilled + 1 helper
Painting151 skilled
Flooring61 skilled + 1 helper