AIM:
To determine the workability of fresh concrete by compacting factor test as per IS: 1199 – 1959.
APPARATUS:
i) Compacting factor apparatus
FIG2:- COMAPCTING FACTOR APPARATUS
PROCEDURE:
- The sample of concrete is placed in the upper hopper upto
the brim. - The trap-door is opened so that the concrete falls into the lower hopper.
- The trap-door of the lower hopper is opened and the concrete is allowed to fall into the cylinder.
- The excess concrete remaining above the top level of the cylinder is then cut off with the help of plane blades.
- The concrete in the cylinder is weighed. This is known as weight of partially compacted concrete.
- The cylinder is filled with a fresh sample of concrete and vibrated to obtain full compaction. The concrete in the cylinder is weighed again. This weight is known as the weight of fully compacted concrete.
RESULTS:

It should normally be stated to the nearest second decimal place.